[Column] Case Study | Shortening Construction Time by Switching from Rappuru Concrete Method
In Kyushu, a certain public building (school) solved construction period issues by switching to the El Niño method. This is a case that achieved a shortened construction period, reduced leftover soil, and provided surface reinforcement.
At a certain public building site in Kyushu (a school building, three stories, partially steel-reinforced concrete), it became clear during the design phase that the initially planned ripple concrete method would not meet the construction schedule. By switching to the Super Ripple Elneed method, we achieved a reduction in construction time, a decrease in excess soil, and surface reinforcement. We spoke with the deputy site manager of the joint venture. ⬛︎ Issue: Overlapping Processes The processes of earth retention, formwork, and soil retention overlapped with curing times, making it difficult to adhere to the construction schedule. ⬛︎ Deciding Factor: "Peace of Mind from Surface Support" After considering columnar improvements, we determined that surface support would be structurally more reassuring. Trust in our extensive construction examples also played a key role in the decision to adopt this method. ⬛︎ Results: Construction Time Reduced as Expected The need for soil retention and formwork construction was eliminated, and the construction time was shortened as anticipated. All strength tests for the test specimens were passed. Underground obstacles were removed as needed, allowing for normal construction procedures. "We highly recommend this approach if you're looking to shorten construction time on a large site," was the feedback we received. ▶ Please feel free to contact us for inquiries about method changes.
basic information
For more details, please download the catalog or feel free to contact us.
Price range
Delivery Time
Applications/Examples of results
For more details, please download the catalog or feel free to contact us.
catalog(3)
Download All CatalogsDistributors
The Elneed Association handles the "Super Rappuru Basic Construction Method (Elneed Method)." This method uses stabilized soil created by mixing construction-generated soil with water and cement-based solidifying agents, and it is an improved version of the Rappuru concrete method for construction foundations. Our member companies are located from Tohoku to Kyushu, allowing us to respond to requests from all over the country. Please feel free to contact us when you need our services.