れんたま【KEMROC】 Official site

New method 'PPE method' for chipping work in repair construction.

Using a cutting machine and a dust suction machine together! Contributing to the improvement of dust dispersion, construction environment, construction period, and costs!

The "PPE Method" is a construction technique used in repair work that contributes to the improvement of dust dispersion, construction environment, construction period, and costs. By attaching a cutting machine to a backhoe, the hydraulic-driven cutting bit cuts the target object while a powerful dust suction machine operates to prevent dust dispersion. By changing the size of the backhoe, it can also accommodate high-altitude work over 10 meters, and the cutting machine comes in five different specifications to adapt to various construction environments. 【Features】 ■ Equipped with a powerful dust suction machine that instantly removes dust ■ Construction is possible in urban areas ■ No need for workers to enter the construction site due to machine operation ■ Over 30% cost reduction compared to manual construction ■ Adjustable cutting thickness from 0 to 190mm *For more details, please refer to the PDF document or feel free to contact us.

Related Link - http://www.rentama.co.jp/

basic information

【Specifications】 ■Construction Quantity: Wall area 25m²/unit/day, Ceiling area 12m²/unit/day ■Construction Machinery, etc.: Backhoe (cutting machine), 4-ton truck, compressor truck, debris collection vehicle ■Personnel Composition (1 team): 1 heavy machinery operator, 1 blade guide, 1 general caretaker, 2 general workers ■Temporary Scaffolding: Not required (manual work with high-altitude work vehicle at corners) ■Dust Control: Not required (powerful dust suction machine) ■Noise: Approximately 60 dB ■Waste Type: Other debris *For more details, please refer to the PDF document or feel free to contact us.

Price range

Delivery Time

Applications/Examples of results

【Applications】 ■ Seismic reinforcement work for road tunnels, bridge piers, etc. ■ Measures against spalling for floor slabs, road tunnels, etc. ■ Neutralization measures for cut-and-cover roads, retaining walls, etc. ■ Surface preparation work for painting on bridges, etc. ■ Precision surface milling work for concrete and asphalt surfaces. *For more details, please refer to the PDF document or feel free to contact us.