ペリー・ジャパン Official site

[Example] "Bario Column No-Separator Method" PERI Column Formwork System

Streamlining construction! We will introduce reference examples of the 'Vario Column No-Separator Method' used on actual sites!

【Site Information】 Site Name: Minebea Co., Ltd. Matsuidamachi New Factory Construction Project Location: Anjō City, Gunma Prefecture, Japan General Contractor: Kajima Corporation Kanto Branch Gunma Office Construction Contractor: Shimura Construction Co., Ltd. System Used: 'Vario Column No-Separator Method' VARIO / Vario Column Formwork System Construction Period: Around May 2016 Minebea Co., Ltd., known for its precision machined parts such as bearings and electronic components like motors, closed its Omori Factory located in Ota City, Tokyo, and built a new factory to relocate its operations to the existing factory site in Matsuidamachi, Anjō City, Gunma Prefecture. There are already two existing factories with a total floor area of 9,606 square meters. The new factory will be a two-story building with a total floor area of approximately 9,000 square meters. 【Proposal Content】 * Use of 'Vario Column No-Separator Method' PERI Vario GT24 Column Formwork System to shorten the construction process * Easy to handle even for first-time users, with good release → Achieved process shortening despite being a cooperating company handling our materials for the first time! ☆ Please download the "PERI Magazine" below and check out other case studies as well! ↓↓ You can also check various achievements from our website ↓↓

Perry Japan Co., Ltd.

basic information

"Vario Column No-Separator Method" Vario Column Formwork System 【Product Features】 ■ Concrete lateral pressure: Capable of handling up to 100 kN/m². ■ Columns with dimensions from 800 to 1200 mm can be constructed without separators. ■ Independent columns for frame elevated bridges, warehouses, etc., can be constructed in one pour. <NETIS Registration Number: KT-180005-A> *For more details, please feel free to contact us.

Price range

Delivery Time

Applications/Examples of results

**On-Site Needs** We have adopted our VARIO column formwork system for this new construction project. Since the columns are of SRC structure, the steel frame construction was already underway; however, the reasons for the adoption include the absence of separators and the ease of repurposing. We have also received feedback from the site indicating that there are benefits in terms of shortening the construction schedule. The formwork sizes are 800 x 800 mm for the first floor, with a height of h=5,770 mm, and for the second floor, heights range from h=4,000 to 4,876 mm. For the second floor, by removing the extended part of the formwork, we can easily accommodate columns of varying heights. We delivered 12 sets of the VARIO column formwork system and used them in two batches of six sets each. Despite this being the first time a partner company handled our materials, we take pride in the fact that the primary reason for the reduction in the construction schedule was that our materials are easy to handle, even for first-time users, and they allow for smooth operation.

Related Videos

[Concrete Construction Method Special Feature] 'Vario Column No-Separator Method'

TECHNICAL

High-strength formwork plywood "PERI Birch" [PEFC certified!]

PRODUCT

Company Profile: Perry Japan Co., Ltd.

COMPANY

[Data] Peri Magazine Third Edition

TECHNICAL

News about this product(1)

Distributors

Recommended products